A Study of the Segment Assembly Error and Quality Control Standard of Special-Shaped Shield Tunnels
March 1, 2023
Abstract
Large-section special-shaped shield tunnels feature many advantages, such as versatility and a large space utilization rate in energy transmission and public transport; however, guaranteeing the quality of segments’ assembly is difficult. Based on the quasi-rectangular shield tunnel project of Hangzhou Line 9 in China, this study investigated the formation mechanism and control measures of lining segment assembly defects. By quantifying the manufacturing error and positioning error, a simulation program for segment assembly is developed to calculate the error. Furthermore, considering the relative accumulative error between the upper and lower T blocks, the finite element model of key blocks (T-LZ block) is established to perform mechanical analysis, based on which the relative error control standard of the key block under the corresponding working conditions is proposed. The results show that the assembly quality can be effectively improved by assembling the LZ block first and applying corresponding error control measures, and the displacement of the segment along the rZ direction should be carefully controlled during the construction. The error caused by normal assembly will not damage the LZ block, and the corresponding control standard under the action of multi-degree-of-freedom error (extreme case) is 9.8 mm. Using this method to predict the assembly quality of segments can provide a basis for actual construction control of segment assembly.
Large-section special-shaped shield tunnels feature many advantages, such as versatility and a large space utilization rate in energy transmission and public transport; however, guaranteeing the quality of segments’ assembly is difficult. Based on the quasi-rectangular shield tunnel project of Hangzhou Line 9 in China, this study investigated the formation mechanism and control measures of lining segment assembly defects. By quantifying the manufacturing error and positioning error, a simulation program for segment assembly is developed to calculate the error. Furthermore, considering the relative accumulative error between the upper and lower T blocks, the finite element model of key blocks (T-LZ block) is established to perform mechanical analysis, based on which the relative error control standard of the key block under the corresponding working conditions is proposed. The results show that the assembly quality can be effectively improved by assembling the LZ block first and applying corresponding error control measures, and the displacement of the segment along the rZ direction should be carefully controlled during the construction. The error caused by normal assembly will not damage the LZ block, and the corresponding control standard under the action of multi-degree-of-freedom error (extreme case) is 9.8 mm. Using this method to predict the assembly quality of segments can provide a basis for actual construction control of segment assembly.
Record ID
Keywords
assembly quality, control standard, error analysis, lining segments, quasi-rectangular shield tunnel
Subject
Suggested Citation
Li P, Dai Z, Wang X, Liu J, Rui Y, Li X, Fan J, Chen P. A Study of the Segment Assembly Error and Quality Control Standard of Special-Shaped Shield Tunnels. (2023). LAPSE:2023.14267
Author Affiliations
Li P: College of Environmental Science and Engineering, Donghua University, Shanghai 201620, China [ORCID]
Dai Z: College of Environmental Science and Engineering, Donghua University, Shanghai 201620, China
Wang X: College of Civil Engineering, Tongji University, Shanghai 200092, China [ORCID]
Liu J: College of Urban Railway Transportation, Shanghai University of Engineering Science, Shanghai 201620, China
Rui Y: College of Civil Engineering, Tongji University, Shanghai 200092, China
Li X: College of Civil Engineering, Tongji University, Shanghai 200092, China
Fan J: Shanghai Tunnel Engineering Co., Ltd., Shanghai 200032, China
Chen P: Shanghai Tunnel Engineering Co., Ltd., Shanghai 200032, China
Dai Z: College of Environmental Science and Engineering, Donghua University, Shanghai 201620, China
Wang X: College of Civil Engineering, Tongji University, Shanghai 200092, China [ORCID]
Liu J: College of Urban Railway Transportation, Shanghai University of Engineering Science, Shanghai 201620, China
Rui Y: College of Civil Engineering, Tongji University, Shanghai 200092, China
Li X: College of Civil Engineering, Tongji University, Shanghai 200092, China
Fan J: Shanghai Tunnel Engineering Co., Ltd., Shanghai 200032, China
Chen P: Shanghai Tunnel Engineering Co., Ltd., Shanghai 200032, China
Journal Name
Energies
Volume
15
Issue
7
First Page
2512
Year
2022
Publication Date
2022-03-29
ISSN
1996-1073
Version Comments
Original Submission
Other Meta
PII: en15072512, Publication Type: Journal Article
Record Map
Published Article

LAPSE:2023.14267
This Record
External Link

https://doi.org/10.3390/en15072512
Publisher Version
Download
Meta
Record Statistics
Record Views
303
Version History
[v1] (Original Submission)
Mar 1, 2023
Verified by curator on
Mar 1, 2023
This Version Number
v1
Citations
Most Recent
This Version
URL Here
https://psecommunity.org/LAPSE:2023.14267
Record Owner
Auto Uploader for LAPSE
Links to Related Works
(0.07 seconds)
[0.08 s]