Highly Renewable District Heat for Espoo Utilizing Waste Heat Sources
March 27, 2023
Abstract
The district heating operator Fortum and the city of Espoo have set a goal to abandon the use of coal in district heating production and increase the share of renewable sources to 95% by the year 2029. Among renewable fuels and heat pumps, waste heat utilization has an important role in Fortum’s plans for the decarbonization of district heating production, and Fortum is considering the possibility of utilizing waste heat from a large data center in its district heating network. The goal of this paper is to investigate the feasibility and required amount of waste heat to achieve this goal. Two different operation strategies are introduced—an operation strategy based on marginal costs and an operation strategy prioritizing waste heat utilization. Each strategy is modeled with three different electricity price scenarios. Because the low temperature waste heat from a data center must be primed by heat pumps, the electricity price has a significant impact on the feasibility of waste heat utilization. Prioritizing waste heat utilization leads to higher production costs, but a lower waste heat capacity is needed to reach the goal of 95% renewables in production. The higher electricity price emphasizes the differences between the two operation strategies. Waste heat utilization also leads to significant reductions of CO2 emissions.
The district heating operator Fortum and the city of Espoo have set a goal to abandon the use of coal in district heating production and increase the share of renewable sources to 95% by the year 2029. Among renewable fuels and heat pumps, waste heat utilization has an important role in Fortum’s plans for the decarbonization of district heating production, and Fortum is considering the possibility of utilizing waste heat from a large data center in its district heating network. The goal of this paper is to investigate the feasibility and required amount of waste heat to achieve this goal. Two different operation strategies are introduced—an operation strategy based on marginal costs and an operation strategy prioritizing waste heat utilization. Each strategy is modeled with three different electricity price scenarios. Because the low temperature waste heat from a data center must be primed by heat pumps, the electricity price has a significant impact on the feasibility of waste heat utilization. Prioritizing waste heat utilization leads to higher production costs, but a lower waste heat capacity is needed to reach the goal of 95% renewables in production. The higher electricity price emphasizes the differences between the two operation strategies. Waste heat utilization also leads to significant reductions of CO2 emissions.
Record ID
Keywords
data center, decarbonization transition, energy system modeling, heat pump, open district heating network, Renewable and Sustainable Energy
Subject
Suggested Citation
Hiltunen P, Syri S. Highly Renewable District Heat for Espoo Utilizing Waste Heat Sources. (2023). LAPSE:2023.24157
Author Affiliations
Hiltunen P: Department of Mechanical Engineering, School of Engineering, Aalto University, P.O. Box 14100, FIN-00076 Aalto, Finland
Syri S: Department of Mechanical Engineering, School of Engineering, Aalto University, P.O. Box 14100, FIN-00076 Aalto, Finland [ORCID]
Syri S: Department of Mechanical Engineering, School of Engineering, Aalto University, P.O. Box 14100, FIN-00076 Aalto, Finland [ORCID]
Journal Name
Energies
Volume
13
Issue
14
Article Number
E3551
Year
2020
Publication Date
2020-07-10
ISSN
1996-1073
Version Comments
Original Submission
Other Meta
PII: en13143551, Publication Type: Journal Article
Record Map
Published Article

LAPSE:2023.24157
This Record
External Link

https://doi.org/10.3390/en13143551
Publisher Version
Download
Meta
Record Statistics
Record Views
234
Version History
[v1] (Original Submission)
Mar 27, 2023
Verified by curator on
Mar 27, 2023
This Version Number
v1
Citations
Most Recent
This Version
URL Here
https://psecommunity.org/LAPSE:2023.24157
Record Owner
Auto Uploader for LAPSE
Links to Related Works
(1.2 seconds) 0.14 + 0.05 + 0.63 + 0.15 + 0 + 0.05 + 0.05 + 0 + 0.05 + 0.08 + 0 + 0