Case Study on Pre-Splitting Blasting Reasonable Parameters of Goaf-Side Entry Retained by Roof Cutting for Hard Main Roof
Hengzhong Zhu, Huajun Wang
February 27, 2023
Abstract
The key parameters of pressure relief pre-splitting blasting technology (PRPBT) contribute to the implementation effect of goaf-side entry by roof cutting (GSERC). This study is an attempt to design the key parameters including the roof cutting height, the roof cutting angle, the spacing between blasting boreholes, the charge structure and the sealing length by using theoretical analysis, numerical simulation and field implementation. The basic quality index of the main roof is 666.27, and combined with the peeping observation result, the main roof belongs to the category of a hard main roof. Different from a weakened roof and a compound roof, the unreasonable parameters of the PRPBT for the hard main roof lead to three problems including an insufficient pre-splitting blasting effect, roof suspension in the goaf and serious damage to the rock mass for the roof cutting rib. The PRPBT effect is closely related to key parameters, including the roof cutting parameters and the pre-splitting blasting parameters. Hence, to solve those three problems, a new design strategy was proposed based on the optimized directions of increasing the roof cutting height, decreasing the spacing between the blasting boreholes, changing the charge structure and adjusting the sealing length. According to the results of the theoretical calculation, numerical simulation and in situ measurement, the roof cutting height, the roof cutting angle, the spaced distance between the blasting boreholes, the charge structure and the sealing length were determined as 10 m, 15°, 500 mm, 4 + 4 + 3 + 3 + 2 and 2.4 m, respectively. The fissure rate was proposed to assess the developed effect of different pre-splitting blasting schemes. The proposed design strategy achieved a better effect of pre-splitting blasting for the entry, and eliminated the roof suspension of the hard main roof in the goaf. The design strategy in this study could contribute to other similar coal mines under the condition of a hard main roof.
Keywords
fissure rate, goaf-side entry by roof cutting, hard main roof, newly designed strategy, pressure relief pre-splitting blasting technology
Suggested Citation
Zhu H, Wang H. Case Study on Pre-Splitting Blasting Reasonable Parameters of Goaf-Side Entry Retained by Roof Cutting for Hard Main Roof. (2023). LAPSE:2023.11252
Author Affiliations
Zhu H: School of Energy and Mining Engineering, Shandong University of Science and Technology, Qingdao 266590, China; State Key Laboratory of Strata Intelligent Control and Green Mining Co-Founded by Shandong Province and the Ministry of Science and Technology, [ORCID]
Wang H: School of Mining and Mechanical Engineering, Liupanshui Normal University, Liupanshui 553000, China
Journal Name
Processes
Volume
11
Issue
2
First Page
350
Year
2023
Publication Date
2023-01-21
ISSN
2227-9717
Version Comments
Original Submission
Other Meta
PII: pr11020350, Publication Type: Journal Article
Record Map
Published Article

LAPSE:2023.11252
This Record
External Link

https://doi.org/10.3390/pr11020350
Publisher Version
Download
Files
Feb 27, 2023
Main Article
License
CC BY 4.0
Meta
Record Statistics
Record Views
265
Version History
[v1] (Original Submission)
Feb 27, 2023
 
Verified by curator on
Feb 27, 2023
This Version Number
v1
Citations
Most Recent
This Version
URL Here
https://psecommunity.org/LAPSE:2023.11252
 
Record Owner
Auto Uploader for LAPSE
Links to Related Works
Directly Related to This Work
Publisher Version
(0.07 seconds)

[0.07 s]