Solving the Two-Crane Scheduling Problem in the Pre-Steelmaking Process
Xie Xie, Yongyue Zheng, Tianwei Mu, Fucai Wan, Hai Dong
February 27, 2023
Abstract
This research is motivated by the practical pre-steelmaking stage in large iron and steel companies, which have steady and heavy demands for the steelmaking production process. Our problem studied the pre-steelmaking stage, which consists of two steps that are needed in each convertor before the steelmaking process. During each step, a necessary transportation must be operated by a crane. In contrast to the classical two-machine flowshop problem during which both machines are fixed, these transporting operations are performed by two mounted, removeable cranes. Our problem is scheduling two-crane operations for the sake of minimizing the last convertors’ completion time (makespan); that is, the last finish time among the total operation of the two cranes is minimized. This study was concerned with resolving the interference between two cranes by determining the sequence of loading operations and how each crane avoids the other in order to let it complete its next operation first. A mixed integer linear programming (MILP) model was developed to represent the problem, and we further present the computational complexity of the problem. The result implies that our problem is very difficult to solve, and it is computationally challenging to solve the model. A special case is provided, which can be optimally solved in polynomial time. Furthermore, an evolutionary algorithm cuckoo search (CS) algorithm was attempted to obtain near-optimal solutions for medium- and large-scale problems. Finally, the efficiency and effectiveness of our methods were validated by numerical results in both simulated instances as well as real data from a practical production process.
Keywords
crane scheduling, cuckoo search algorithm, mixed integer linear programming, steelmaking
Suggested Citation
Xie X, Zheng Y, Mu T, Wan F, Dong H. Solving the Two-Crane Scheduling Problem in the Pre-Steelmaking Process. (2023). LAPSE:2023.11442
Author Affiliations
Xie X: Key Laboratory of Manufacturing Industrial and Integrated Automation, Shenyang University, Shenyang 110044, China
Zheng Y: Liaoning Inspection Examination & Certification Center, Shenyang 110032, China
Mu T: School of Architecture & Civil Engineering, Shenyang University of Technology, Shenyang 110023, China
Wan F: Key Laboratory of Manufacturing Industrial and Integrated Automation, Shenyang University, Shenyang 110044, China
Dong H: Key Laboratory of Manufacturing Industrial and Integrated Automation, Shenyang University, Shenyang 110044, China
Journal Name
Processes
Volume
11
Issue
2
First Page
549
Year
2023
Publication Date
2023-02-10
ISSN
2227-9717
Version Comments
Original Submission
Other Meta
PII: pr11020549, Publication Type: Journal Article
Record Map
Published Article

LAPSE:2023.11442
This Record
External Link

https://doi.org/10.3390/pr11020549
Publisher Version
Download
Files
Feb 27, 2023
Main Article
License
CC BY 4.0
Meta
Record Statistics
Record Views
218
Version History
[v1] (Original Submission)
Feb 27, 2023
 
Verified by curator on
Feb 27, 2023
This Version Number
v1
Citations
Most Recent
This Version
URL Here
https://psecommunity.org/LAPSE:2023.11442
 
Record Owner
Auto Uploader for LAPSE
Links to Related Works
Directly Related to This Work
Publisher Version
(0.32 seconds)